Audit of Existing Cabinet
Name: City of Perth
Client: City of Perth
Owner: City of Perth
Site Location: State Library
Completed: 28/10/2015
Personnel:
Project Manager: Joseph Arrigo
Site Supervisor: Ryan Sommerfeld
Special Project Achievements:
All works were completed within the deadlines and under budget.
Quality Standards Applicable:
AS/NZS 3080:2013
AS/ACIF S009:2013
Specific OH & S Requirements:
AS/NZS 3012:2010
Audit of existing Cabinet for the Rack migration works at the City of Perth State Library.
Project works required the removal and replacement of existing communication cabinets and installation and migration of a new APC cabinet solution.
As the state library car park is in operation near to a full time basis works needed to be coordinated so as no downtime occurred to critical, Ticketing, Security, Boom gate and access control systems.
Works required the shutting down and relocating of Servers , Switches , Optic Fibre cables as well as many different systems feed via Copper, Cat 6, CCTV and PA system cables.
Systematic pre-works mapped all existing copper and fibre cables identifying CPP with a cut over method to upgrade the current Comms room without any downtime to the State Library car park.